Widen exit ramps and add auxiliary lanes @ Cherry, Citrus & Cedar Ave Interchanges |
Description: In Fontana at Cherry, Citrus and Cedar Ave interchanges - Widen ramps and construct auxiliary lanes
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Bernardino |
City | Bloomington, Fontana, Rialto |
Zip Code | 92316, 92335, 92337 |
Senate District |
32 |
Assembly District | 62 |
Congressional District | 43 |
Caltrans District |
08 |
County/State Route | San Bernardino 10 |
Postmile Begin/End | 12 19.8 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Additional Auxiliary Lane Miles | 4.7 | |
Daily Travel Time Savings (hours) | 3095 | 3577 |
Lane Miles Added (Mixed) | 5 | |
Peak Period Time Savings (minutes) | 246465 | 284880 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Robert So | (909) 383-4513 | robert.so@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Robert So | (909) 383-4513 | robert.so@dot.ca.gov | |
Right of Way Phase |
Caltrans | Robert So | (909) 383-4513 | robert,so@dot.ca.gov | |
Construction Phase |
Caltrans | Robert So | (909) 383-4513 | robert.so@dot.ca.gov | |
Corridor System Management Plan |
Caltrans | Rena Tan | (909) 806-3927 | rena.tang@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $0 | $0 | ||||
CMIA |
$19,233 | $-8,323 | $10,910 | ||||
SHOPP Augmentation |
$0 | $8,369 | $8,369 | ||||
Non-bond Funding | |||||||
State/Federal* |
$13,460 | $-13,330 | $130 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $32,693 | $-13,284 | $19,409 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$1,200 | $-550 | $650 | $647 | |||
Design(PS&E) |
$1,900 | $-230 | $1,670 | $1,759 | |||
Right of Way |
$570 | $0 | $570 | $14 | |||
Construction |
$29,023 | $-12,504 | $16,519 | $12,760 | |||
Total* | $32,693 | $-13,284 | $19,409 | $15,180 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
07/01/2007 01/01/2008 |
|
07/05/2007 01/03/2008 |
100 | 07/01/2007 01/03/2008 |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/01/2007 08/02/2009 |
|
01/04/2008 08/10/2009 |
100 | 01/04/2008 08/10/2009 |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
01/01/2008 06/01/2009 |
|
01/04/2008 05/22/2009 |
100 | 01/04/2008 05/22/2009 |
0 0 |
|
Begin Construction Phase
End Construction Phase |
12/08/2009 12/01/2010 |
|
10/12/2010 12/20/2012 |
100 | 10/12/2010 12/20/2012 |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
02/01/2011 06/01/2011 |
|
12/21/2012 12/19/2014 |
0 | 12/21/2012 12/19/2014 |
0 0 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 05/01/2008 | 05/01/2008 | 0 | 0 | |||
Implementation Date | 06/01/2008 | 06/01/2008 | 0 | 0 |
????????
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Additional Auxiliary Lane Miles | 4.7 | |
Daily Travel Time Savings (hours) | 3095 | 3577 |
Lane Miles Added (Mixed) | 5 | |
Peak Period Time Savings (minutes) | 246465 | 284880 |
Bond Funding Cost | |
---|---|
Adopted: |
$19,233,000 |
Current Approved: |
$8,880,000 |
Actual Expenditures: |
$8,207,000 |
Status as of December 31, 2023.